CA Intermediate · Cost and Management Accounting · Standard Costing
Standard data for a product of Kaveri Chemicals: 10 kg of material per unit at Rs 20 per kg. Actual output for the month was 500 units. Actual material used was 5,200 kg at a cost of Rs 1,09,200. Which statement about the variances is correct?
Material cost variance is Rs 9,200 Adverse, made up of a price variance of Rs 5,200 Adverse and a usage variance of Rs 4,000 Adverse. Standard cost is Rs 1,00,000, actual price is Rs 21 per kg, and 200 kg extra was used at the standard Rs 20.
- AMaterial cost variance Rs 9,200 Adverse; price variance Rs 5,200 Adverse; usage variance Rs 4,000 AdverseCorrect
- BMaterial cost variance Rs 9,200 Adverse; price variance Rs 4,000 Adverse; usage variance Rs 5,200 Adverse
- CMaterial cost variance Rs 9,200 Adverse; price variance Rs 5,200 Favourable; usage variance Rs 4,000 Adverse
- DMaterial cost variance Rs 5,200 Adverse; price variance Rs 5,200 Adverse; usage variance Rs 4,000 Adverse
Explanation
Standard quantity = 500 x 10 = 5,000 kg; standard cost = Rs 1,00,000. MCV = 1,00,000 - 1,09,200 = Rs 9,200 A. Actual price = 1,09,200/5,200 = Rs 21, so price variance = (20 - 21) x 5,200 = Rs 5,200 A. Usage variance = (5,000 - 5,200) x 20 = Rs 4,000 A. Check: 5,200 + 4,000 = 9,200.
Did you get it right without looking?
One question tells you little. A timed set on Standard Costing shows your real accuracy, how long you take and where you lose marks.
More Standard Costing questions
- Which statement about a standard costing system is correct?
- Kaveri Plastics Ltd. fixes the standard for a moulded part at 4 kg of resin per unit at Rs 90 per kg. In March, it produced 1,500 units and …
- Kaveri Components budgeted to make 5,000 units of a product in a month with standard labour of 3 hours per unit at Rs 80 per hour. Actual pr…
- Standard Costing: Sharma Industries has a standard of 8 labour hours per unit at Rs 30 per hour. In a month, 1,000 units were produced. Hour…
- Kaveri Auto Components fixes a standard of 4 labour hours per unit at Rs 150 per hour. In March it produced 1,500 units. Labour hours paid w…
- Bharat Castings budgets fixed overhead of Rs 6,00,000 for 20,000 units (standard 2 hours per unit, 40,000 hours). In the month, the actual f…