Standard labour rate is $12 per hour. A production team was staffed with more highly skilled workers paid $14 per hour, and 5,000 hours were worked against a standard allowance of 5,200 hours for actual output. What are the labour rate and labour efficiency variances?

The rate variance is $10,000 adverse (5,000 hours paid $2 more than standard) and the efficiency variance is $2,400 favourable (200 hours saved at the $12 standard rate). Efficiency is valued at standard rate, not the actual $14.

  1. ARate $10,000 adverse; efficiency $2,400 favourableCorrect
  2. BRate $10,000 adverse; efficiency $2,800 favourable
  3. CRate $10,000 favourable; efficiency $2,400 adverse
  4. DRate $2,400 adverse; efficiency $10,000 favourable

Explanation

Rate variance: 5,000 x ($12 - $14) = $10,000 adverse. Efficiency variance: (5,200 - 5,000) x $12 = $2,400 favourable, valued at the standard rate. The use of skilled labour explains an adverse rate but favourable efficiency.