ACCA Applied Knowledge · Management Accounting · Monitoring performance and reporting
Standard labour rate is $12 per hour. A production team was staffed with more highly skilled workers paid $14 per hour, and 5,000 hours were worked against a standard allowance of 5,200 hours for actual output. What are the labour rate and labour efficiency variances?
The rate variance is $10,000 adverse (5,000 hours paid $2 more than standard) and the efficiency variance is $2,400 favourable (200 hours saved at the $12 standard rate). Efficiency is valued at standard rate, not the actual $14.
- ARate $10,000 adverse; efficiency $2,400 favourableCorrect
- BRate $10,000 adverse; efficiency $2,800 favourable
- CRate $10,000 favourable; efficiency $2,400 adverse
- DRate $2,400 adverse; efficiency $10,000 favourable
Explanation
Rate variance: 5,000 x ($12 - $14) = $10,000 adverse. Efficiency variance: (5,200 - 5,000) x $12 = $2,400 favourable, valued at the standard rate. The use of skilled labour explains an adverse rate but favourable efficiency.
Did you get it right without looking?
One question tells you little. A timed set on Monitoring performance and reporting shows your real accuracy, how long you take and where you lose marks.
More Monitoring performance and reporting questions
- A company's standard cost for a product is 3 kg of material at $4 per kg. For 1,000 units, 3,300 kg were purchased and used at a total cost …
- Kelvin Co budgeted sales of 5,000 units at $20 each with a standard variable cost of $12 per unit and fixed costs of $18,000. Actual sales w…
- A company's budgeted fixed production overhead was $60,000 for 20,000 machine hours, absorbed per machine hour. Actual output required 19,00…
- A manager cuts the selling price below standard to boost demand. Actual sales are 12,000 units against a budget of 10,000 units. The standar…
- Dunmore Co has sales of $2,400,000, operating profit of $288,000, and capital employed of $1,600,000. Management plans to cut operating cost…
- In an operating statement prepared under standard marginal costing, which of the following is the correct starting point and treatment of a …