ACCA Applied Knowledge · Management Accounting · Monitoring performance and reporting
A company's budgeted fixed production overhead was $60,000 for 20,000 machine hours, absorbed per machine hour. Actual output required 19,000 standard machine hours, and actual fixed overhead expenditure was $62,000. What is the fixed overhead volume variance?
The fixed overhead volume variance is $3,000 adverse. The rate is $3 per hour, so 19,000 standard hours absorb $57,000 against a budget of $60,000. Output was lower than budgeted, so less overhead was absorbed, giving an adverse variance.
- A$3,000 adverseCorrect
- B$3,000 favourable
- C$2,000 adverse
- D$5,000 adverse
Explanation
Absorption rate = $60,000 / 20,000 = $3 per hour. Absorbed = 19,000 x $3 = $57,000. Volume variance = $57,000 - $60,000 = $3,000 adverse. The expenditure variance is $2,000 adverse; the total under-absorption is $5,000.
Did you get it right without looking?
One question tells you little. A timed set on Monitoring performance and reporting shows your real accuracy, how long you take and where you lose marks.
More Monitoring performance and reporting questions
- A hotel records the percentage of guests who rate their stay as good or excellent. Which type of performance measure is this?
- Borea Co has a standard of 3 labour hours per unit at $12 per hour. In June it produced 1,400 units and paid for 4,400 hours, of which 4,200…
- Brecon Co's results: sales $1,200,000; operating profit $144,000; capital employed $960,000. Management plans to cut costs so operating prof…
- Standard labour rate is $12 per hour. A production team was staffed with more highly skilled workers paid $14 per hour, and 5,000 hours were…
- Which of the following is the most likely explanation for a favourable material price variance combined with an adverse material usage varia…
- Zeta Co budgeted to produce 5,000 units using 2 kg of material per unit at a standard price of $4 per kg. Actual output was 5,200 units, usi…