Sundaram Textiles is evaluating a machine that costs Rs 1,00,000 today and will produce a single cash inflow of Rs 1,21,000 at the end of year 2. The cost of capital is 10% per annum. What is the NPV of the project?

The NPV is zero. Discounting the Rs 1,21,000 inflow two years at 10% gives a present value of Rs 1,00,000, which equals the initial outlay. The project therefore earns exactly the cost of capital, so its IRR is 10%.

  1. ARs 0Correct
  2. BRs 21,000
  3. CRs 10,000
  4. DRs 1,21,000
  5. Rs 17,355

Explanation

PV of inflow = 1,21,000 / 1.1^2 = 1,21,000 / 1.21 = Rs 1,00,000. NPV = 1,00,000 - 1,00,000 = 0. Rs 21,000 is the undiscounted profit, which ignores the time value of money.