Sunrise Actuarial Consultants Pvt Ltd in Pune agreed to deliver a valuation report to an insurer by 30 June. The contract did not say time was of the essence, and the report was delivered five days late. The insurer suffered no identifiable loss. Which statement best describes the insurer's position under general Indian contract principles?

The insurer can claim damages for any loss caused by the delay but cannot normally terminate, because time was not of the essence. Late performance is still a breach, but it is not serious enough to discharge the contract, and without loss the damages would be minimal.

  1. AIt may treat the contract as discharged and refuse to pay anything, because any delay is a repudiatory breach
  2. BIt may claim damages for any loss caused by the delay, but cannot ordinarily terminate, as time was not essentialCorrect
  3. CIt may obtain specific performance of the delay, forcing the consultants to deliver the report earlier
  4. DIt may recover the full contract price back as a penalty for lateness
  5. It has no remedy at all, because late performance is never a breach

Explanation

Where time is not of the essence, late performance is a breach, but it normally entitles the innocent party only to damages for proven loss. It does not give a right to end the contract. Here no loss was shown, so damages would be small or nominal. Treating the contract as discharged is wrong because the delay is not a repudiatory breach.

Did you get it right without looking?

One question tells you little. A timed set on Implied terms, exclusion of liability, contractual remedies and damages shows your real accuracy, how long you take and where you lose marks.

More Implied terms, exclusion of liability, contractual remedies and damages questions