Sunrise Actuarial Consultants engaged Mr Rao to deliver a valuation report by 30 June, and the contract expressly stated that timely delivery was a condition. Mr Rao delivered on 5 July, a minor delay with no loss to the firm. Under Indian contract law principles, what is the position?
Sunrise may terminate, because the parties expressly made timely delivery a condition. Breach of a condition gives the innocent party the right to end the contract regardless of how small the actual loss, and it may also claim damages for any loss.
- ASunrise may terminate and treat the contract as repudiated, because breach of a condition entitles the innocent party to do soCorrect
- BSunrise may only claim damages, because any breach of a condition is treated as a warranty if no loss arises
- CSunrise may only seek specific performance, because termination is unavailable for late delivery
- DSunrise has no remedy, because no loss was suffered
- The contract is automatically void, because the delay occurred before delivery
Explanation
A condition is a term going to the root of the contract. Breach entitles the innocent party to terminate and claim damages, whether or not much loss follows. Distractors wrongly downgrade the term or claim the contract is void automatically.
Did you get it right without looking?
One question tells you little. A timed set on Implied terms, exclusion of liability, contractual remedies and damages shows your real accuracy, how long you take and where you lose marks.
More Implied terms, exclusion of liability, contractual remedies and damages questions
- Apex Pensions contracts with Dr Iyer for a mortality study. The agreement states that all terms are conditions, including a clause requiring…
- Meridian Re agreed to supply a reinsurance quote to Orchid General by a fixed date, stated to be vital to a regulatory filing. Meridian deli…
- A contract between Nisha Insurance Brokers and a client states that on breach the defaulting party will pay Rs 5 lakh. The actual loss cause…
- A pension-valuation firm's contract states: 'The firm shall not be liable for any errors in the report.' An analyst, Karan, knowingly alters…
- An actuarial consultancy, Meridian Advisory, contracts to deliver a pricing model to an insurer by 30 June. The contract says nothing on whe…
- Anita Rao Associates contracts to build a mortality model for an insurer. Clause 9 limits liability 'for breach of this agreement to the fee…