CA Intermediate · Advanced Accounting · AS 7 Construction Contracts
Tapi Projects Ltd. has a fixed price contract of Rs 120 lakh. Cumulative costs incurred are Rs 90 lakh and estimated costs to complete are Rs 60 lakh. Revenue and cost recognised in earlier years: revenue Rs 50 lakh, costs Rs 50 lakh. Under AS 7, what is the total foreseeable loss to be recognised immediately, and what is the loss to be charged in the current year (over and above amounts already recognised)?
The full expected loss of Rs 30 lakh must be recognised at once. Since earlier years showed no profit or loss, the entire Rs 30 lakh falls in the current year, so none of the offered current-year figures except the full amount is right.
- ATotal Rs 30 lakh; current year Rs 30 lakh
- BTotal Rs 30 lakh; current year Rs 12 lakh
- CTotal Rs 30 lakh; current year Rs 18 lakhCorrect
- DTotal Rs 30 lakh; current year Rs 0
Explanation
Total cost = 90+60 = 150; price 120; expected loss 30 lakh, recognised immediately in full. Completion = 90/150 = 60%; cumulative revenue 72 lakh. Cumulative cost 90, so loss on work done = 18 lakh. Earlier profit/loss was nil (50 vs 50). Provision for the remaining expected loss = 30-18 = 12 lakh. Current year charge = 18 + 12 = 30 lakh. Check: total loss 30, earlier nil, so current year bears all 30.
Did you get it right without looking?
One question tells you little. A timed set on AS 7 Construction Contracts shows your real accuracy, how long you take and where you lose marks.
More AS 7 Construction Contracts questions
- Sagar Constructions Ltd has a fixed price contract of ₹80 lakh. Estimated total cost is ₹60 lakh throughout the contract. Costs incurred are…
- At the year end, Kaveri Engineering Ltd has one contract in progress. Contract costs incurred to date are ₹900 lakh, recognised profits are …
- Meridian Infra Ltd is building a flyover for a state government under a construction contract. Its accountant is listing the costs for the c…
- Shivalik Constructions Ltd has a fixed price contract of ₹1,000 lakh. At the year end, costs incurred to date are ₹480 lakh, which include ₹…
- Himalaya Projects Ltd has a fixed-price contract of ₹200 lakh with total estimated contract cost of ₹150 lakh. Costs incurred to date are ₹9…
- Malwa Engineers undertakes a contract. Which of the following costs would be excluded from contract costs under AS 7 because they cannot be …