CA Intermediate · Advanced Accounting · AS 7 Construction Contracts
At the year end, Kaveri Engineering Ltd has one contract in progress. Contract costs incurred to date are ₹900 lakh, recognised profits are ₹150 lakh and recognised losses are ₹30 lakh. Progress billings to date are ₹800 lakh. Applying AS 7 disclosure requirements, what is the gross amount due from customers for contract work?
The gross amount due from customers is ₹220 lakh. It equals costs incurred of ₹900 lakh plus recognised profits of ₹150 lakh, less recognised losses of ₹30 lakh, less progress billings of ₹800 lakh. The positive balance means work done exceeds amounts billed.
- A₹250 lakh
- B₹220 lakhCorrect
- C₹1,020 lakh
- D₹20 lakh
Explanation
Gross amount due from customers = costs incurred + recognised profits − recognised losses − progress billings. This is 900 + 150 − 30 − 800 = ₹220 lakh. Ignoring the recognised losses gives ₹250 lakh, and omitting progress billings gives ₹1,020 lakh.
Did you get it right without looking?
One question tells you little. A timed set on AS 7 Construction Contracts shows your real accuracy, how long you take and where you lose marks.
More AS 7 Construction Contracts questions
- In 2025-26, Vindhya Engineers Ltd incurred ₹3 lakh on tendering for a bridge contract and charged it to the statement of profit and loss bec…
- Narmada Constructions Ltd. has a fixed price contract of Rs 200 lakh. Year 1: costs incurred Rs 60 lakh, estimated further costs Rs 90 lakh.…
- Tapi Projects Ltd. has a fixed price contract of Rs 120 lakh. Cumulative costs incurred are Rs 90 lakh and estimated costs to complete are R…
- Kaveri Builders Ltd has a fixed price contract of ₹50 lakh for a warehouse. At the end of the first year, costs incurred are ₹28 lakh, which…
- Tulsi Constructions Ltd. has a fixed price contract for Rs 120 lakh. At the end of Year 1, costs incurred are Rs 48 lakh and estimated costs…
- Yamuna Engineering reports on one fixed price contract at year end. Contract costs incurred plus recognised profits (no recognised losses) a…