The first unit of a job took 40 hours. The total time for the first two units was 64 hours. Using the cumulative average time model, what learning rate is implied?
The implied learning rate is 80%. The average time for two units is 64 divided by 2, which is 32 hours. Dividing this by the first unit's 40 hours gives 80%. Using the second unit's 24 hours instead would wrongly give 60%.
- A60%
- B64%
- C160%
- D80%Correct
Explanation
The cumulative average time for 2 units is 64 / 2 = 32 hours. The learning rate is 32 / 40 = 80%. The 60% figure wrongly uses the second unit's time of 24 hours divided by 40.
Did you get it right without looking?
One question tells you little. A timed set on Analytical techniques in budgeting and forecasting shows your real accuracy, how long you take and where you lose marks.
More Analytical techniques in budgeting and forecasting questions
- The first unit of a product takes 125 labour hours. An 80% learning curve applies (cumulative average time model) and labour costs $15 per h…
- A business buys two materials. Base-year prices: X $4, Y $10. Current prices: X $5, Y $12. Base-year quantities: X 100 units, Y 50 units. Wh…
- A business finds r = 0.5 between staff training hours and units processed per hour. Which conclusion is most appropriate?
- A cost accountant calculates a correlation coefficient of -0.80 between the selling price of a product and the quantity sold. What is the co…
- A company finds that the correlation coefficient between advertising spend and sales revenue is +0.9. Which statement is the most appropriat…
- Which of the following is a recognised limitation of using expected values in budgeting?