The first unit of a product takes 125 labour hours. An 80% learning curve applies (cumulative average time model) and labour costs $15 per hour. What is the expected labour cost of units 5 to 8 inclusive?
The labour cost of units 5 to 8 is $2,880. Four units take 320 hours (80 hour average) and eight units take 512 hours (64 hour average). The difference is 192 hours, which at $15 per hour costs $2,880.
- A$3,840
- B$2,880Correct
- C$4,800
- D$7,680
Explanation
Average for 4 units is 125 x 0.8 x 0.8 = 80 hours, so total is 320 hours. Average for 8 units is 80 x 0.8 = 64 hours, so total is 512 hours. Units 5-8 take 512 - 320 = 192 hours, costing 192 x $15 = $2,880. $3,840 wrongly applies the 8-unit average of 64 hours to just four units.
Did you get it right without looking?
One question tells you little. A timed set on Analytical techniques in budgeting and forecasting shows your real accuracy, how long you take and where you lose marks.
More Analytical techniques in budgeting and forecasting questions
- A company finds that the correlation coefficient between monthly advertising spend and monthly sales revenue is +0.9. What is the coefficien…
- Zeta Co estimates demand for a new product as follows: 2,000 units with probability 0.30, 3,000 units with probability 0.50 and 4,000 units …
- The first unit of a job took 40 hours. The total time for the first two units was 64 hours. Using the cumulative average time model, what le…
- A business buys two materials. Base-year prices: X $4, Y $10. Current prices: X $5, Y $12. Base-year quantities: X 100 units, Y 50 units. Wh…
- A business finds r = 0.5 between staff training hours and units processed per hour. Which conclusion is most appropriate?
- The first unit of a product takes 250 labour hours and an 80% learning curve applies. What is the total time expected for the first 4 units?