ACCA Applied Knowledge · Management Accounting · Analytical techniques in budgeting and forecasting
The first unit of a product takes 250 labour hours and an 80% learning curve applies. What is the total time expected for the first 4 units?
The first four units take 640 hours in total. Doubling output twice gives a cumulative average time of 250 x 80% x 80%, which is 160 hours per unit. Multiplying by four units gives 640 hours. Quoting 160 hours would give only the average.
- A160 hours
- B800 hours
- C1,000 hours
- D640 hoursCorrect
Explanation
Output doubles twice from 1 to 4 units, so the cumulative average time is 250 x 0.8 x 0.8 = 160 hours per unit. Total time is 160 x 4 = 640 hours. 160 hours is only the average per unit, and 1,000 hours ignores learning entirely.
Did you get it right without looking?
One question tells you little. A timed set on Analytical techniques in budgeting and forecasting shows your real accuracy, how long you take and where you lose marks.
More Analytical techniques in budgeting and forecasting questions
- Which of the following is a recognised limitation of using expected values in budgeting?
- In a multiplicative model with four quarters, the seasonal indices for Quarters 1 to 3 are 0.80, 1.20 and 1.10. Actual sales in Quarter 4 we…
- Analysis of a company's monthly overhead cost against production volume gives a coefficient of determination of 0.49, with a positive regres…
- A cost accountant calculates a correlation coefficient of -0.80 between the selling price of a product and the quantity sold. What is the co…
- Monthly sales of a product were 40, 46 and 52 units in January, February and March. What is the three-month moving average, which is placed …
- In which situation is learning curve theory MOST likely to be applicable?