CS Professional · Corporate Restructuring, Valuation and Insolvency · Liquidation on or after Failing of Resolution Plan

Under a pre-packaged insolvency resolution process, the NCLT admitted the application of Orion Components Ltd and declared a moratorium. The committee of creditors approves a resolution plan under section 54K, but the plan does not change the management or control of the corporate debtor to a person who was not a promoter or in its management. The NCLT had earlier passed an order under section 54J(2). What must the NCLT do under section 54L(4)?

The NCLT must reject the plan, terminate the pre-packaged process and pass a liquidation order, and declare that the pre-pack process costs are included in the liquidation costs. Section 54L(4) mandates this where the plan does not shift management or control away from promoters or existing management.

  1. AApprove the plan, since the committee of creditors has approved it
  2. BReturn the plan to the committee of creditors for modification within thirty days
  3. CReject the plan, terminate the process and pass a liquidation order, with the pre-pack process costs included in the liquidation costsCorrect
  4. DReject the plan and direct a fresh pre-packaged process with a new moratorium

Explanation

Section 54L(4) says that in such a case the Adjudicating Authority shall pass an order rejecting the plan, terminating the pre-packaged process with a liquidation order under section 33(1)(b), and declaring that the pre-pack costs form part of the liquidation costs. It is mandatory, so approval or remand is not available.