FRM Part II · FRM Exam Part II · Supervisory Guidance on Model Risk Management
Under supervisory guidance on model risk management (SR 11-7 style), which statement best describes the role of a bank's board of directors in model risk governance?
The board approves the model risk management framework and oversees senior management's implementation of it. Validation, development and parameter calibration are operational activities performed by validators, developers and model owners, not by the board, which is responsible for tone, accountability and overall oversight.
- AApproving the model risk management framework and ensuring senior management implements it, with overall oversight of model riskCorrect
- BPerforming independent validation of each material model before it is placed in production
- CDeveloping and back-testing the models used by trading desks
- DSetting the numerical parameters of each model to keep output within risk appetite
Explanation
The board sets the tone, approves the firm-wide model risk policy and holds senior management accountable for implementation. It does not carry out validation or development work, which belong to independent validators and model owners/developers. Parameter setting is an operational task for model developers.
Did you get it right without looking?
One question tells you little. A timed set on Supervisory Guidance on Model Risk Management shows your real accuracy, how long you take and where you lose marks.
More Supervisory Guidance on Model Risk Management questions
- A developer selects a model's input data for a mortgage prepayment model and finds that the available history covers only a low-rate period.…
- Which element is most important for a bank's model inventory to support aggregate model risk management that includes vendor models?
- Under supervisory guidance, a bank's model outputs are routinely overridden by loan officers. What is the most appropriate management respon…
- A bank uses a vendor valuation model for structured products. The vendor releases a version update that changes the calibration routine with…
- A bank's VaR model at 99% confidence is backtested over 250 days and produces 9 exceptions. The validator compares this with the 2.5 expecte…
- A risk manager is asked what a bank's model risk policy should say when a model with known limitations must be used before validation is com…