Under the Halsey premium plan, a worker at Pune Tools is paid Rs 50 per hour. The time allowed for a job is 40 hours and the worker completes it in 30 hours. The bonus is 50% of time saved, paid at the hourly rate. What is the total earning of the worker for the job?
Total earnings are Rs 1,750. The worker gets Rs 1,500 for 30 hours actually worked, plus a Halsey bonus of 50% of the 10 hours saved at Rs 50 per hour, which is Rs 250. Adding the two gives Rs 1,750.
- ARs 1,500
- BRs 1,750Correct
- CRs 2,000
- DRs 1,875
Explanation
Time saved = 40 - 30 = 10 hours. Wages for time taken = 30 x 50 = Rs 1,500. Bonus = 50% x 10 x 50 = Rs 250. Total = Rs 1,750. Rs 1,500 omits the bonus; Rs 2,000 pays full time-allowed wages, which is the Rowan/time-rate-guaranteed error.
Did you get it right without looking?
One question tells you little. A timed set on Employee Cost and Direct Expenses shows your real accuracy, how long you take and where you lose marks.
More Employee Cost and Direct Expenses questions
- Ananya Textiles pays under the Halsey premium plan. Standard time for a job is 40 hours, actual time taken is 30 hours, and the hourly rate …
- In a factory, the time spent by workers because of a power failure, for which they are paid wages but no production takes place, is called i…
- Meenakshi Textiles pays under Rowan plan. The time rate is Rs 60 per hour, time allowed is 40 hours and time taken is 30 hours. What is the …
- Sharma Tools pays a worker under the Halsey premium plan. Standard time for a job is 40 hours, time taken is 30 hours, the wage rate is Rs. …
- Sharma Fabricators pays a worker under the Rowan plan. Standard time for a job is 20 hours, the hourly rate is Rs 80, and the worker finishe…
- Which one of the following is treated as a direct expense of a job rather than as overhead?