CMA Intermediate · Cost Accounting · Budget and Budgetary Control
Verma Ltd budgets credit purchases of Rs 1,60,000 in June and Rs 2,00,000 in July. Suppliers are paid 60% in the month after purchase and 40% in the second month after purchase. May credit purchases were Rs 1,00,000. What is the cash payment to suppliers in July?
July payment to suppliers is 60% of June purchases (Rs 96,000) plus 40% of May purchases (Rs 40,000), giving Rs 1,36,000. Payments lag purchases by one and two months, so July's own purchases are not paid in July.
- ARs 1,36,000Correct
- BRs 1,60,000
- CRs 1,76,000
- DRs 1,20,000
Explanation
July payment = 60% of June purchases + 40% of May purchases = 96,000 + 40,000 = Rs 1,36,000. Using 60% of July purchases (Rs 1,20,000) would wrongly pay in the month of purchase. Check: 0.6x1,60,000=96,000; 0.4x1,00,000=40,000.
Did you get it right without looking?
One question tells you little. A timed set on Budget and Budgetary Control shows your real accuracy, how long you take and where you lose marks.
More Budget and Budgetary Control questions
- In a flexible-budget-based production cost budget, which item stays constant in total when production rises within the relevant range?
- Which of the following is the principal budget factor (key factor) for a firm whose sales demand is unlimited but whose output is restricted…
- Which of the following is correctly treated as an item NOT to be included while preparing a cash budget of a manufacturing company?
- A company budgets sales of 12,000 units. Opening stock of finished goods is 1,500 units and the closing stock is planned at 20% of next peri…
- Sharma Components Ltd budgets at 10,000 units: variable cost Rs 30 per unit and fixed cost Rs 2,00,000. What is the flexible budget total co…
- In the sequence of preparing a master budget for a manufacturing company, which budget is normally prepared first once the principal budget …