CMA Intermediate · Cost Accounting · Budget and Budgetary Control

Verma Ltd budgets credit purchases of Rs 1,60,000 in June and Rs 2,00,000 in July. Suppliers are paid 60% in the month after purchase and 40% in the second month after purchase. May credit purchases were Rs 1,00,000. What is the cash payment to suppliers in July?

July payment to suppliers is 60% of June purchases (Rs 96,000) plus 40% of May purchases (Rs 40,000), giving Rs 1,36,000. Payments lag purchases by one and two months, so July's own purchases are not paid in July.

  1. ARs 1,36,000Correct
  2. BRs 1,60,000
  3. CRs 1,76,000
  4. DRs 1,20,000

Explanation

July payment = 60% of June purchases + 40% of May purchases = 96,000 + 40,000 = Rs 1,36,000. Using 60% of July purchases (Rs 1,20,000) would wrongly pay in the month of purchase. Check: 0.6x1,60,000=96,000; 0.4x1,00,000=40,000.

Did you get it right without looking?

One question tells you little. A timed set on Budget and Budgetary Control shows your real accuracy, how long you take and where you lose marks.

More Budget and Budgetary Control questions