Verma Ltd's budgeted overhead is Rs 1,50,000 at 60% capacity and Rs 1,70,000 at 80% capacity. Assuming the overhead is semi-variable, what is the budgeted overhead at 70% capacity?
The budgeted overhead at 70% capacity is Rs 1,60,000. The variable element is Rs 1,000 per 1% of capacity and fixed overhead is Rs 90,000, so 90,000 + 70 x 1,000 equals Rs 1,60,000, the midpoint of the two given levels.
- ARs 1,60,000Correct
- BRs 1,65,000
- CRs 1,55,000
- DRs 1,40,000
Explanation
Variable cost per 1% capacity = (1,70,000 - 1,50,000)/20 = Rs 1,000. Fixed = 1,50,000 - 60,000 = Rs 90,000. At 70%: 90,000 + 70,000 = Rs 1,60,000. Check: midpoint of 1,50,000 and 1,70,000 is 1,60,000. The other values do not follow the linear relation.
Did you get it right without looking?
One question tells you little. A timed set on Budget and Budgetary Control shows your real accuracy, how long you take and where you lose marks.
More Budget and Budgetary Control questions
- A municipal corporation uses performance budgeting for its road repair programme. Budgeted target: 80 km of road at a standard cost of Rs 2,…
- A flexible budget differs from a fixed (static) budget mainly because a flexible budget:
- Under zero-base budgeting, the starting point for preparing the budget of a department is:
- In Zero Base Budgeting (ZBB), the first step in preparing the budget for a department is to:
- Which feature distinguishes Performance Budgeting from traditional line-item budgeting?
- Nirmal Tools expects sales of 10,000 units in April and 12,000 in May. It keeps closing finished stock equal to 25% of next month's sales. M…