Which of the following best describes a stepped fixed cost when preparing a flexed budget?

A stepped fixed cost stays constant within a relevant range of activity and then jumps to a higher level once that range is exceeded, for example extra supervisors or a new machine. Flexed budgets must reflect the step when activity moves outside the range.

  1. AA cost that rises in proportion to activity
  2. BA cost that stays constant within a relevant range of activity but jumps when that range is exceededCorrect
  3. CA cost that falls per unit as activity rises but is zero at nil activity
  4. DA cost that is unaffected by activity at all levels

Explanation

A stepped cost is fixed within a range of activity, such as supervisors needed per 1,000 units, and then increases in a step. Proportional costs are variable, and costs unaffected at all levels are purely fixed.