Which of the following best describes the treatment of fixed costs when a budget is flexed to a higher activity level within the relevant range?
Total fixed costs remain unchanged when a budget is flexed within the relevant range. Because the total stays constant, the fixed cost per unit falls as activity rises. Only variable costs, and any stepped costs crossing a threshold, change.
- AFixed costs per unit remain unchanged
- BTotal fixed costs remain unchangedCorrect
- CTotal fixed costs increase in proportion to activity
- DFixed costs are removed from the flexed budget
Explanation
Within the relevant range, total fixed costs stay constant when activity changes, so fixed cost per unit falls as output rises. Treating fixed costs as varying with activity is the typical error.
Did you get it right without looking?
One question tells you little. A timed set on Flexible budgets shows your real accuracy, how long you take and where you lose marks.
More Flexible budgets questions
- Which of the following best describes a stepped fixed cost when preparing a flexed budget?
- Delta Co's budget for 8,000 units shows variable overheads of $24,000 and fixed overheads of $16,000. Actual output was 9,000 units and actu…
- A department's budgeted overhead is $30,000 for 5,000 machine hours and $38,000 for 7,000 machine hours. Using the high-low method, what is …
- Which cost would a flexible budget leave unchanged when activity rises from 10,000 to 11,000 units, assuming the relevant range is not excee…
- Budgeted figures for 8,000 units are: variable costs $96,000 and fixed costs $40,000. Actual output was 9,000 units with actual total costs …
- Which statement best describes why a flexible budget is preferred to a fixed budget for budgetary control when actual activity differs from …