Which of the following best describes the purpose of the 'rating' step in a stopwatch time study?
Rating converts observed times into the time a qualified worker would take working at a normal pace. The analyst judges the operator's speed against a standard of 100 and adjusts the observed time, giving basic time, before allowances are added to reach standard time.
- ATo select the most suitable worker for the job based on seniority
- BTo compute the number of observations needed for a given confidence level
- CTo convert observed times into times a qualified worker would take working at normal paceCorrect
- DTo add allowances for fatigue and personal needs to the basic time
Explanation
Rating compares the observed worker's pace with the concept of a normal pace so that observed time can be adjusted to basic (normal) time. Allowances are added after rating to obtain standard time, so the allowance option describes a later step.
Did you get it right without looking?
One question tells you little. A timed set on Control Measures - Time and Motion Study, Method Study, Work Study shows your real accuracy, how long you take and where you lose marks.
More Control Measures - Time and Motion Study, Method Study, Work Study questions
- A simo-chart (simultaneous motion cycle chart) is best described as:
- For a packing task at a Nashik firm, the average observed time is 3.00 minutes, the operator rating is 90 on a standard of 100, and allowanc…
- In motion study, the basic elementary movements into which any manual operation can be broken down, such as 'Grasp', 'Transport Empty' and '…
- Using a standard time of 5 minutes per unit, how many units should a worker produce in an 8-hour shift if 40 minutes of the shift are lost t…
- A workshop supervisor at a Pune firm replaces hand-holding of a component with a clamp fixture, so that both hands are free for productive w…
- A task has a basic time of 8 minutes. Allowances are expressed as 20% of the standard time (i.e., of the total time including allowances), n…