CMA Intermediate · Operations Management and Strategic Management · Control Measures - Time and Motion Study, Method Study, Work Study
Which of the following is an effective (productive) therblig, one that directly advances the work, rather than an ineffective one that should be reduced or eliminated?
Assemble is the effective therblig because it directly advances the job by joining parts. Search, select and hold are ineffective elements that add delay or tie up a hand without progressing the work, so motion study tries to reduce or eliminate them.
- ASearch
- BAssembleCorrect
- CSelect
- DHold
Explanation
Assemble directly adds value by progressing the work, so it is an effective therblig. Search and Select are ineffective mental or perceptual delays, and Hold generally is a non-productive therblig that fixtures can replace, freeing the hand.
Did you get it right without looking?
One question tells you little. A timed set on Control Measures - Time and Motion Study, Method Study, Work Study shows your real accuracy, how long you take and where you lose marks.
More Control Measures - Time and Motion Study, Method Study, Work Study questions
- A stopwatch study of a packing task at an Indian FMCG plant records a mean observed time of 1.8 minutes per cycle at a rating of 110. Relaxa…
- In the basic procedure of method study, which step comes immediately after 'Record' the relevant facts of the existing method?
- In a time study, a worker's observed performance is judged to be 120% against the standard (normal) rating of 100. The mean observed time fo…
- A flow process chart of a component records: 6 operations, 3 inspections, 4 transports, 2 delays and 1 storage. What is the total number of …
- Which chart is most suitable for recording the movements of the left and right hands of a worker performing a bench assembly task, so that t…
- In a micro-motion study of an assembly task filmed at 1,000 frames per minute, a cycle is recorded as 2,400 frames. A study of the same cycl…