ACCA Applied Knowledge · Management Accounting · Standard costing system
A company's standard labour rate was $14 per hour. Because of a shortage of skilled workers, it used more highly skilled staff paid $16 per hour. Which is the most likely resulting pattern of labour variances?
An adverse rate variance and possibly a favourable efficiency variance is the likely pattern. Staff were paid $16 against a $14 standard, so the rate variance is adverse. Because skilled workers usually produce faster, fewer hours may be used than standard, which can create a favourable efficiency variance.
- AAdverse rate variance and possibly favourable efficiency varianceCorrect
- BFavourable rate variance and adverse efficiency variance
- CAdverse rate variance and adverse idle time variance
- DFavourable rate variance and favourable efficiency variance
Explanation
Paying $16 against a $14 standard gives an adverse rate variance. More skilled workers usually work faster, so fewer hours may be needed, giving a possibly favourable efficiency variance. A favourable rate variance would require pay below standard, which contradicts the data.
Did you get it right without looking?
One question tells you little. A timed set on Standard costing system shows your real accuracy, how long you take and where you lose marks.
More Standard costing system questions
- Budgeted production was 5,000 units at a standard fixed overhead of $6 per unit (budgeted fixed overheads $30,000). Actual output was 4,600 …
- Why is a flexed budget used in variance analysis, rather than comparing actual results directly with the original fixed budget?
- Which of the following is the most appropriate description of a standard cost card for a product?
- A company sets its standard cost card for Product Z at 4 kg of material at $5 per kg, 2 hours of labour at $12 per hour, and variable overhe…
- Which of the following is a primary purpose of operating a standard costing system in a manufacturing company?
- A company sets its standard labour rate using a standard that assumes all staff are paid at grade B, $12 per hour. Production in the period …