CMA Intermediate · Operations Management and Strategic Management · Operations Planning
Which of the following is a pure strategy in aggregate planning that uses only demand-side influence rather than adjusting production capacity?
Shifting demand through promotions and off-peak pricing is the demand-side option. The other choices, hiring and layoffs, overtime and undertime, and subcontracting, all adjust supply or capacity to match demand rather than influencing when customers buy.
- AVarying the workforce size through hiring and layoffs
- BUsing overtime and undertime
- CSubcontracting part of the work
- DShifting demand through promotions and off-peak pricingCorrect
Explanation
Hiring, layoffs, overtime and subcontracting are capacity (supply) options. Promotions and off-peak pricing change the demand pattern to fit capacity, so they are the demand-side option.
Did you get it right without looking?
One question tells you little. A timed set on Operations Planning shows your real accuracy, how long you take and where you lose marks.
More Operations Planning questions
- A packaged-snacks company in Pune wants to forecast next quarter's sales of a new flavour for which no sales history exists. It decides to c…
- Sundaram Auto Parts has a design capacity of 1,200 units per week and an effective capacity of 1,000 units per week. Actual output last week…
- In the hierarchy of operations planning, which of the following correctly places the Master Production Schedule (MPS) relative to aggregate …
- A manufacturer arranges its machines so that all lathes are in one section, all drilling machines in another and all milling machines in a t…
- A plant in Pune has a design capacity of 1,000 units per day and an effective capacity of 800 units per day. Actual output is 640 units per …
- In the hierarchy of operations planning, which decision is classified as a long-range (strategic) operations planning decision rather than a…