ACCA Applied Skills · Performance Management · Budgetary systems and types of budget
Which of the following is a recognised feature of zero-based budgeting (ZBB)?
In zero-based budgeting, each activity is set out in a decision package and ranked by priority, with funding allocated down the ranking until resources are exhausted. Nothing is assumed from past spending, unlike incremental budgeting.
- AEach activity is described in a decision package and ranked in order of priorityCorrect
- BBudgets are updated each month by adding a further month to the end of the plan
- CPrior-year spending is taken as the starting point and adjusted for inflation
- DBudgets are set by senior management and imposed on departments without consultation
Explanation
ZBB requires managers to prepare decision packages for each activity, which are then ranked and funded in priority order until resources run out. Adding a month is rolling budgeting, using last year's spend is incremental budgeting, and imposition describes an imposed style of participation, not ZBB.
Did you get it right without looking?
One question tells you little. A timed set on Budgetary systems and types of budget shows your real accuracy, how long you take and where you lose marks.
More Budgetary systems and types of budget questions
- Brindle Ltd budgeted sales of 5,000 units with variable cost of $6 per unit and fixed cost of $20,000. Actual sales were 4,500 units, and ac…
- Which of the following best describes the role of the budget committee in the budget preparation process?
- A company's managers each prepare their own budgets and submit them to senior management for review and approval. What is this approach call…
- Which statement about a fixed budget is correct?
- A manager argues that next year's budget for the maintenance department should simply be this year's figure increased by expected inflation …
- A company prepares a budget for the next twelve months. At the end of each quarter, the quarter just ended is dropped and a new quarter is a…