CS Executive · Corporate Accounting and Financial Management · Capital Budgeting
Which of the following is the most common reason why NPV and IRR can rank mutually exclusive projects differently?
Conflicts arise mainly from differences in the timing of cash flows (and scale or life), because NPV assumes reinvestment at the cost of capital while IRR assumes reinvestment at the project's own IRR, so rankings can differ when the discount rate lies below the crossover rate.
- ADifferences in the timing pattern of cash flows, which implies different reinvestment rate assumptionsCorrect
- BUse of straight-line depreciation in one project only
- CBoth projects having the same initial outlay and the same life
- DProjects having a positive NPV at the cost of capital
Explanation
NPV assumes intermediate cash flows are reinvested at the cost of capital, while IRR assumes reinvestment at the IRR itself. When the timing of inflows differs, the rankings can reverse at rates below the crossover rate. Same outlay and life would not by themselves cause such a conflict in general.
Did you get it right without looking?
One question tells you little. A timed set on Capital Budgeting shows your real accuracy, how long you take and where you lose marks.
More Capital Budgeting questions
- Under single-period capital rationing, Anand Ltd has ₹10 lakh available. Divisible projects: A needs ₹4 lakh with NPV ₹2 lakh; B needs ₹4 la…
- Rohan Pharma is considering a project costing Rs 1,00,000 that produces Rs 60,000 at the end of each of the next 2 years. Using the discount…
- Ananya Textiles is evaluating a project with an initial outlay of Rs 2,00,000 that gives a single cash inflow of Rs 2,42,000 at the end of y…
- Mahalaxmi Textiles buys a machine for Rs 12,00,000 that generates uniform annual cash inflows of Rs 3,00,000 after tax. What is the payback …
- In capital budgeting, the certainty-equivalent approach to handling risk works by:
- A project generates additional annual cash revenue of Rs 8,00,000 and cash expenses of Rs 5,00,000, with annual depreciation of Rs 1,00,000.…