Project A costs ₹1,00,000 and returns ₹1,30,000 after one year. Project B costs ₹1,00,000 and returns ₹1,66,000 after two years... Instead, consider the crossover rate concept: at a discount rate of 10%, Project X has NPV ₹8,000 and Project Y has NPV ₹5,000. At the crossover rate both have equal NPV. If Y ranks higher than X at 15%, which statement is correct?

The crossover rate lies between 10% and 15%. X has the higher NPV at 10% while Y has the higher NPV at 15%, so the NPV profiles must intersect between those two discount rates, where both projects have equal NPV.

  1. AThe crossover rate is below 10%
  2. BThe crossover rate lies between 10% and 15%Correct
  3. CThe crossover rate is above 15%
  4. DThe crossover rate cannot exist for two projects

Explanation

At 10% X has the higher NPV, and at 15% Y has the higher NPV. The ranking therefore reverses somewhere between these rates, which is where the NPV profiles cross. The crossover is the rate at which both NPVs are equal.