Which statement about flexed budgets is correct?

A flexed budget compares actual results with a budget restated to the actual activity level. This gives a like-for-like comparison. It depends on knowing which costs are fixed and which are variable, and fixed costs are not changed in proportion to activity.

  1. AA flexed budget changes fixed costs in proportion to activity
  2. BA flexed budget compares actual results with a budget adjusted to actual activity levelCorrect
  3. CA flexed budget is prepared before the period to cover all possible activity levels only
  4. DA flexed budget removes the need to identify cost behaviour

Explanation

A flexed budget restates budgeted costs and revenues to the actual activity level so that like is compared with like. This requires knowing cost behaviour, and fixed costs stay constant within the relevant range.

Did you get it right without looking?

One question tells you little. A timed set on Budget preparation shows your real accuracy, how long you take and where you lose marks.

More Budget preparation questions