IAI Actuarial Core Principles · Business Finance · Cost of capital and evaluating investment projects
Which statement about using WACC as the discount rate for a new project is most appropriate?
WACC is suitable as the project discount rate only when the project has similar business risk to the firm and does not change its capital structure. Otherwise a risk-adjusted rate reflecting the project's own risk should be used.
- AIt is valid for any project regardless of risk
- BIt is valid only if the project has similar business risk to the existing firm and leaves the capital structure unchangedCorrect
- CIt should always be replaced by the cost of debt
- DIt should use book values of equity rather than market values
- It should exclude the tax shield on debt
Explanation
WACC reflects the risk and financing mix of the existing firm. It is appropriate only when the project has similar business risk and does not alter the gearing materially. For projects with different risk, a project-specific rate is needed.
Did you get it right without looking?
One question tells you little. A timed set on Cost of capital and evaluating investment projects shows your real accuracy, how long you take and where you lose marks.
More Cost of capital and evaluating investment projects questions
- Mehta Textiles is considering a machine costing Rs 10,00,000. Expected net cash inflows are Rs 3,00,000 in year 1, Rs 4,00,000 in year 2, Rs…
- A firm's capital structure at market values is equity Rs 300 crore and debt Rs 100 crore. Cost of equity is 14%, pre-tax cost of debt is 8%,…
- Which statement about the internal rate of return (IRR) of a conventional project is correct?
- Using the Capital Asset Pricing Model, Kaveri Textiles Ltd has an equity beta of 1.2. The risk-free return is 7% per annum and the expected …
- Which item should be used to compute the equity weight in a WACC calculation?
- A company ranks two mutually exclusive projects. Project X has the shorter payback period and the higher ARR, while Project Y has a higher N…