ACCA Strategic Professional · Strategic Business Leader · Identification, assessment and measurement of risk
Zenith Hydro, a utility, has a board statement saying it will accept a maximum of 5% variation in annual project cost overruns before escalating to the board. Which risk concept does this statement most precisely describe?
This is risk tolerance. Tolerance sets the acceptable variation around a specific objective, here a 5% cost overrun before escalation. Appetite is the broader strategic level of risk the board will pursue, and capacity is the maximum risk the firm could absorb.
- ARisk appetite, being the overall amount and type of risk the organisation is willing to pursue to achieve objectives
- BRisk tolerance, being the acceptable level of variation in performance relative to a specific objectiveCorrect
- CRisk capacity, being the maximum risk the organisation can bear before failing
- DRisk culture, being the shared values and behaviours towards risk
Explanation
A numerical limit on acceptable deviation for a specific objective (project cost) is risk tolerance. Appetite is broader and strategic, usually stated for the organisation as a whole. Capacity is the absolute ceiling, far beyond an escalation trigger at 5%.
Did you get it right without looking?
One question tells you little. A timed set on Identification, assessment and measurement of risk shows your real accuracy, how long you take and where you lose marks.
More Identification, assessment and measurement of risk questions
- Brightwave Telecom's CEO is paid a bonus only if reported profit exceeds a target. The finance director notices that the CEO has pressed sta…
- Karel Mining's board is described as risk seeking. It has just approved entry into an unstable region with high expected returns, though its…
- Lumen Bank has a risk-averse stated appetite, but its traders receive large bonuses tied only to annual trading profit, and several have bre…
- Zenith Foods assesses a supplier-failure risk with a 20% annual probability and an estimated loss of $500,000 if it occurs. A second risk, a…
- Orchid Pharma is considering entering an emerging market. The board identifies risks that include currency depreciation, political instabili…
- Calder Retail has a risk of stock-outs with a likelihood judged high and an impact judged low, because each event costs little and customers…