ACCA Strategic Professional · Strategic Business Reporting (International) · Provisions, contingencies and events after the reporting period
Zenith plc decides on 15 December 20X5 to close a factory. Detailed formal plans were approved by the board on that date, but the plan was not announced to employees, customers or suppliers until 20 January 20X6. The reporting date is 31 December 20X5 and the financial statements are authorised on 25 February 20X6. How should the closure costs be treated in the year ended 31 December 20X5 under IAS 37?
No provision is recognised at 31 December 20X5. A restructuring obligation needs a detailed formal plan plus a valid expectation raised in those affected, by starting implementation or announcing it. The announcement came after the reporting date, so it is a non-adjusting event and is disclosed if material.
- ARecognise a restructuring provision at 31 December 20X5 because the board approved a detailed formal plan
- BDo not recognise a provision at 31 December 20X5 because no valid expectation had been raised in those affected by the reporting date; consider disclosure of the announcement as a non-adjusting eventCorrect
- CRecognise a provision at 31 December 20X5 because the announcement occurred before the financial statements were authorised, treating it as an adjusting event
- DRecognise a provision only for the redundancy costs, but not for the costs of closing the site
Explanation
A restructuring constructive obligation arises only when there is a detailed formal plan and the entity has raised a valid expectation in those affected by starting to implement the plan or announcing its main features. This had not happened by 31 December 20X5. The announcement in January 20X6 is a non-adjusting event, so the board decision alone (option A) is insufficient.
Did you get it right without looking?
One question tells you little. A timed set on Provisions, contingencies and events after the reporting period shows your real accuracy, how long you take and where you lose marks.
More Provisions, contingencies and events after the reporting period questions
- Kestrel Ltd is defending a claim for damages brought by a customer. Kestrel's lawyers advise that it is possible, but less likely than not, …
- Marlow Group has a year end of 30 June 20X6 and the financial statements were authorised on 10 September 20X6. On 5 August 20X6 the board de…
- Nimbus plc's year end is 31 December. In its draft accounts, a contingent liability for a customer's claim is disclosed because outflow was …
- Orion Ltd operates an oil terminal. On 1 January 20X4 it brought the terminal into use and had a legal obligation to dismantle it after 10 y…
- Delta Group, a listed parent, is finalising its financial statements to 31 March 20X6. It operates in a country where a new law, enacted in …
- On 15 December 20X5, the board of Marlow Group approved a detailed plan to close a division, but on 31 December 20X5 (year end) it had not t…