ACCA Strategic Professional · Advanced Financial Management · Discounted cash flow techniques
Zenith plc is appraising a project with a base-case NPV of $2.40 million, calculated by discounting operating cash flows at the ungeared cost of equity. Financing side effects: issue costs of $0.30 million and a present value of tax shield on debt interest of $0.85 million. What is the APV?
The APV is $2.95 million. It equals the base-case NPV of $2.40 million plus the $0.85 million present value of the debt tax shield, less the $0.30 million issue costs, because financing benefits are added and financing costs are deducted.
- A$2.95 millionCorrect
- B$2.55 million
- C$1.75 million
- D$3.55 million
Explanation
APV = base-case NPV + PV of tax shield - issue costs = 2.40 + 0.85 - 0.30 = $2.95 million. Option $3.55m adds the issue costs instead of deducting them. Option $1.75m deducts the tax shield instead of adding it.
Did you get it right without looking?
One question tells you little. A timed set on Discounted cash flow techniques shows your real accuracy, how long you take and where you lose marks.
More Discounted cash flow techniques questions
- A company has a one-period capital constraint, and projects X, Y and Z are divisible. A linear programming formulation gives a shadow price …
- Varley plc is appraising a project with an initial outlay of $200,000 now and a single net cash inflow of $242,000 at the end of year 2. The…
- A proxy company has an equity beta of 1.20, a debt beta of zero, and a market value gearing of debt:equity of 1:3. Tax is 25%. Using the for…
- A company is appraising a project using a nominal (money) cost of capital. Which treatment of cash flows is consistent?
- Kestrel plc is appraising a project. It has already spent $120,000 on a feasibility study, and a further $30,000 of head-office overhead wil…
- Under capital rationing in a single period where projects are divisible and not repeatable, which approach correctly ranks projects to maxim…