A company can launch a product (NPV $200,000 if demand is high, $60,000 if medium, -$120,000 if low) or not launch it (NPV nil). Demand probabilities are high 0.40, medium 0.35 and low 0.25. What is the maximum amount the company should pay for perfect information about demand?

The most the company should pay is $30,000. Without information the launch has an expected NPV of $71,000. With perfect information it avoids launching when demand is low, giving an expected $101,000. The difference of $30,000 is the value of perfect information.

  1. A$30,000Correct
  2. B$71,000
  3. C$101,000
  4. D$120,000

Explanation

EV of launching without information = 80,000 + 21,000 - 30,000 = $71,000. With perfect information the company launches only when demand is high or medium: 80,000 + 21,000 = $101,000. The value of perfect information = 101,000 - 71,000 = $30,000. $71,000 is the EV without information, and $101,000 is the EV with information, not the gain from it.

Did you get it right without looking?

One question tells you little. A timed set on Adjusting for risk and uncertainty in investment appraisal shows your real accuracy, how long you take and where you lose marks.

More Adjusting for risk and uncertainty in investment appraisal questions