ACCA Applied Knowledge · Management Accounting · Summarising and analysing data
A company uses regression analysis to model total production overhead as y = 12,000 + 4.5x, where x is machine hours. Budgeted activity for next month is 3,000 machine hours. What is the forecast overhead cost?
The forecast overhead is 25,500. Substitute 3,000 machine hours into the equation: variable cost is 4.5 multiplied by 3,000, which is 13,500, and adding the fixed element of 12,000 gives the total of 25,500.
- A25,500Correct
- B13,500
- C12,000
- D31,500
Explanation
Overhead = 12,000 + (4.5 x 3,000) = 12,000 + 13,500 = 25,500. The 13,500 option omits the fixed cost. The 31,500 option wrongly multiplies 4.5 by 3,000 and adds 18,000 instead of 12,000.
Did you get it right without looking?
One question tells you little. A timed set on Summarising and analysing data shows your real accuracy, how long you take and where you lose marks.
More Summarising and analysing data questions
- A company analyses the number of customer complaints received each day. Which description correctly classifies this data?
- A production supervisor records the number of defective units found in five batches: 12, 15, 9, 20 and 14. What is the range of this data se…
- A production supervisor records the number of units completed in seven shifts: 42, 38, 45, 38, 50, 41 and 38. What is the mode of this data …
- A set of monthly cost observations has a mean of $50 and a standard deviation of $8. Each observation is multiplied by 2 and then $10 is sub…
- The correlation coefficient between two variables is -0.8. What is the coefficient of determination, and what does it mean?
- A multiplicative model is used for monthly demand. The trend for next month is forecast at 2,000 units and the seasonal index for that month…