Sharma Builders is constructing a bridge. Work certified is ₹40,00,000 and the contractee retains 10% of it as retention money. Cash received so far is ₹30,00,000. How much remains due from the contractee on account of certified work, excluding the retention money?

The balance due is ₹6,00,000. Retention money is 10% of ₹40,00,000, which is ₹4,00,000, so cash receivable on certified work is ₹36,00,000. Deducting ₹30,00,000 already received leaves ₹6,00,000 still to be collected, excluding the retention.

  1. A₹6,00,000Correct
  2. B₹10,00,000
  3. C₹4,00,000
  4. D₹3,60,000

Explanation

Retention = 10% of 40,00,000 = 4,00,000. Cash receivable on certified work = 40,00,000 − 4,00,000 = 36,00,000. Cash already received 30,00,000, so balance due = 6,00,000. The option ₹10,00,000 ignores retention money (40,00,000 − 30,00,000).

Did you get it right without looking?

One question tells you little. A timed set on Contract Costing shows your real accuracy, how long you take and where you lose marks.

More Contract Costing questions