A contractor in Jaipur estimates that 18 workers can complete a road-repair job in 30 days. Because of a deadline, the job must be completed in 20 days. Assuming all workers are equally efficient, how many workers are needed?
The contractor needs 27 workers. Number of workers varies inversely with the days available, so total work stays at 18 × 30 = 540 worker-days. Dividing 540 by the 20 days allowed gives 27 workers to finish the job on time.
- A12
- B20
- C27Correct
- D36
Explanation
Workers vary inversely with days, so workers × days is constant: 18 × 30 = 540 worker-days. Workers needed = 540/20 = 27. Check: 27 × 20 = 540. Choosing 12 comes from wrongly treating the relation as direct (18 × 20/30).
Did you get it right without looking?
One question tells you little. A timed set on Ratios, Variations and Proportions shows your real accuracy, how long you take and where you lose marks.
More Ratios, Variations and Proportions questions
- A firm's monthly sales to purchases are in the ratio 7:5. If sales for a month are ₹4,90,000, what is the amount of purchases?
- The ratio of two numbers is 5:3. If 4 is added to each, the ratio becomes 3:2. What is the sum of the original numbers?
- At Gupta Mills, 12 workers complete an order in 15 days. Because of a deadline change, the order must be finished in 9 days, with every work…
- Rajesh and Meena start a business with capital of ₹60,000 and ₹90,000 respectively. If the year's profit is ₹1,25,000 and it is shared in th…
- A varies directly as B and inversely as the square of C. When B = 8 and C = 2, A = 6. Find A when B = 12 and C = 3.
- If a:b = b:c = 2:3 (a continued proportion), and a = 16, what is the value of c?