ACCA Strategic Professional · Advanced Performance Management · Budgetary planning and control
A divisional manager receives a monthly report showing a large adverse materials price variance caused by a supplier price rise imposed by head office's new central purchasing contract. Which principle of responsibility accounting does this best illustrate?
Managers should be held responsible only for costs and variances they can control. Because the price rise resulted from head office's central contract, the variance is uncontrollable at divisional level and should be reported separately, avoiding unfair performance assessment and demotivation.
- AVariances should be investigated only when controllable by the manager, so this should be reported as uncontrollableCorrect
- BThe manager should be fully accountable because the cost sits in their division
- CAdverse variances should be removed from reports entirely
- DPrice variances are always the production manager's responsibility
Explanation
Responsibility accounting holds managers accountable for items they can influence. The price rise stems from a head-office contract, so it is outside the manager's control and should be identified separately. Holding the manager fully accountable would be demotivating.
Did you get it right without looking?
One question tells you little. A timed set on Budgetary planning and control shows your real accuracy, how long you take and where you lose marks.
More Budgetary planning and control questions
- Kestrel Foods plc starts its annual budget each year by taking last year's actual results and adding 3% for inflation. Managers are not aske…
- Dunmore Retail's sales director participates in setting her budget and negotiates a sales target that she knows is comfortably achievable, w…
- Linden Care, a not-for-profit hospice, receives a fixed annual grant and donations. Its managers argue that budgets should start from the ne…
- Tovar Ltd's budget for a project has a mean cost of 500,000 with a standard deviation of 50,000, assumed normally distributed. Using normal …
- Calder Retail's finance director criticises the annual fixed budget because it is set months ahead and is rarely revisited, even when market…
- Kestrel Software has a highly stable, predictable cost base and a hierarchical culture with limited manager autonomy. The board proposes to …