ACCA Strategic Professional · Advanced Performance Management · Budgetary planning and control
Zentra Ltd produces a single product. Its monthly semi-variable maintenance cost was 41,000 at 2,000 machine hours and 53,000 at 3,000 machine hours. Using the high-low method, what is the budgeted maintenance cost for 2,500 machine hours?
The budgeted cost is 47,000. The high-low method gives a variable cost of 12 per machine hour from the change in cost over the change in hours, and fixed cost of 17,000. At 2,500 hours the cost is 17,000 plus 30,000.
- A47,000Correct
- B44,000
- C50,000
- D49,500
Explanation
Variable rate = (53,000 - 41,000) / (3,000 - 2,000) = 12 per hour. Fixed cost = 41,000 - (2,000 x 12) = 17,000. Budget at 2,500 hours = 17,000 + (2,500 x 12) = 47,000. Option 44,000 would result from ignoring part of the fixed cost, and 50,000 from using the wrong activity level.
Did you get it right without looking?
One question tells you little. A timed set on Budgetary planning and control shows your real accuracy, how long you take and where you lose marks.
More Budgetary planning and control questions
- A divisional manager receives a monthly report showing a large adverse materials price variance caused by a supplier price rise imposed by h…
- Dalton Retail's budgeted sales were 5,000 units at $20, with a standard contribution of $8 per unit. Actual sales were 4,600 units at $21. V…
- Tarn Engineering evaluates plant managers using a budget-constrained style, so a manager is judged solely on meeting the budgeted cost every…
- Marlow Ltd budgeted 8,000 units with variable overhead of $5 per unit and fixed overhead of $40,000. Actual output was 9,000 units and actua…
- Quorra Software develops products in a fast-changing, innovative sector. Its CEO is considering replacing the traditional annual budget with…
- Brightwell Retail, a stable, decentralised group, is deciding how to set divisional budgets. Divisional managers have detailed local market …