CA Foundation · Quantitative Aptitude · Linear Inequalities

A firm makes x units of product M and y units of product N. Each unit of M needs 2 hours of machine time and each unit of N needs 3 hours. Only 24 machine hours are available. Which of the following production plans is feasible?

This item is invalid because more than one option satisfies 2x + 3y ≤ 24.

  1. Ax = 6, y = 4
  2. Bx = 9, y = 2
  3. Cx = 3, y = 6Correct
  4. Dx = 4, y = 5

Explanation

The constraint is 2x + 3y ≤ 24. Option 1 uses 12 + 12 = 24, which is feasible. Option 3 uses 6 + 18 = 24, also feasible. So several options fit, and the question is flawed.

Did you get it right without looking?

One question tells you little. A timed set on Linear Inequalities shows your real accuracy, how long you take and where you lose marks.

More Linear Inequalities questions