A firm makes x units of A and y units of B. Each unit of A needs 2 hours on a machine and each unit of B needs 3 hours; at most 60 machine hours are available. Also, at least 5 units of A must be made and y ≥ 4. What is the maximum possible number of units of B?

The maximum is 16 units of B. B is largest when A is at its minimum of 5 units, using 10 hours and leaving 50 hours. Dividing by 3 hours per unit gives 16.67, so only 16 whole units can be made.

  1. A16Correct
  2. B18
  3. C14
  4. D17

Explanation

Constraints: 2x + 3y ≤ 60, x ≥ 5, y ≥ 4. B is maximum when x is minimum, x = 5, which uses 10 hours. Then 3y ≤ 50, so y ≤ 16.67; as units are whole, y = 16. Option 18 comes from ignoring the minimum x of 5 (x = 3 style error).