CA Intermediate · Cost and Management Accounting · Job Costing
A job costing firm finds that factory overheads absorbed during the year were ₹4,80,000 while actual factory overheads incurred were ₹5,10,000. Which statement correctly describes the position and the usual treatment if the difference is due to normal reasons?
Overheads are under-absorbed by ₹30,000 because absorbed overheads of ₹4,80,000 fall short of actual ₹5,10,000. This unrecovered cost is a loss, so when due to normal causes it is debited to the costing profit and loss account.
- AOverheads are over-absorbed by ₹30,000, and the amount is credited to the costing profit and loss account
- BOverheads are under-absorbed by ₹30,000, and the amount is debited to the costing profit and loss accountCorrect
- COverheads are under-absorbed by ₹30,000, and the amount is credited to the costing profit and loss account
- DOverheads are over-absorbed by ₹30,000, and the amount is debited to the costing profit and loss account
Explanation
Absorbed ₹4,80,000 is less than actual ₹5,10,000, so overheads are under-absorbed by ₹30,000. Under-absorption means costs were not fully recovered through jobs, so it is a loss debited to the costing profit and loss account when it arises from normal causes. Over-absorption would be credited.
Did you get it right without looking?
One question tells you little. A timed set on Job Costing shows your real accuracy, how long you take and where you lose marks.
More Job Costing questions
- Kaveri Fabricators is working on Job No. 214. Direct materials cost Rs 48,000 and direct wages are 600 hours at Rs 80 per hour. Factory over…
- Mehta Printers quoted for Job P-7 at cost plus 25% on selling price (i.e., profit is 25% of the selling price). The job's total cost was ₹96…
- Which statement about work-in-progress and job costing is correct?
- Gupta Printers has a job with direct material Rs 24,000 and direct labour Rs 16,000. Factory overhead is absorbed at 75% of direct labour co…
- Sharma Fabricators uses a machine-hour rate to absorb factory overheads. Budgeted factory overheads for the year are Rs 7,20,000 and budgete…
- Which of the following best describes the nature of a job costing system?