CA Intermediate · Cost and Management Accounting · Job Costing
Which of the following best describes the nature of a job costing system?
Job costing accumulates costs separately for each customer order or specific job because each job is identifiable and distinct. A job cost sheet records materials, labour and overheads for every job. Averaging costs over continuous output belongs to process costing.
- ACosts are accumulated for each customer order or specific job, which is separately identifiableCorrect
- BCosts are accumulated department-wise and averaged over all units produced in a period
- CCosts are accumulated only for continuous mass production of identical units
- DCosts are accumulated for each operation and divided by the total equivalent units
Explanation
Job costing is used where work is carried out against specific customer orders and each job is distinct. Costs are collected on a job cost sheet for each job. Averaging over a department's output describes process costing, not job costing.
Did you get it right without looking?
One question tells you little. A timed set on Job Costing shows your real accuracy, how long you take and where you lose marks.
More Job Costing questions
- Verma Engineering completed Job K-9 with total cost of ₹2,40,000, including factory overheads absorbed at a predetermined rate of ₹40 per ma…
- Sharma Fabricators worked on Job J-21. Direct materials were Rs 48,000 and direct wages Rs 30,000 (1,500 labour hours at Rs 20 per hour). Fa…
- Surya Printers uses a predetermined overhead rate based on machine hours. Budgeted overheads were Rs 9,60,000 for 12,000 machine hours. Actu…
- Sharma Fabricators absorbs factory overhead at Rs 40 per machine hour. Job J-21 used direct material of Rs 18,000, direct labour of Rs 12,00…
- Anand Interiors completed a job with a cost of Rs 1,20,000. During production, abnormal spoilage specific to a customer's special instructio…