CMA Intermediate · Operations Management and Strategic Management · Project Management, Monitoring and Control
An activity has a normal time of 10 days at a normal cost of ₹40,000 and a crash time of 6 days at a crash cost of ₹52,000. Assuming linear cost behaviour, what is its crash cost slope per day?
The crash cost slope is ₹3,000 per day. The extra cost of crashing is 52,000 minus 40,000, which is ₹12,000, and this buys a reduction of 4 days (10 minus 6), so 12,000 divided by 4 gives ₹3,000 per day.
- A₹2,000
- B₹3,000Correct
- C₹4,000
- D₹1,200
Explanation
Crash slope = (Crash cost − Normal cost) / (Normal time − Crash time) = (52,000 − 40,000) / (10 − 6) = 12,000 / 4 = ₹3,000 per day. Using the crash time of 6 days as the divisor gives ₹2,000, which is wrong because the time saved is 4 days, not 6.
Did you get it right without looking?
One question tells you little. A timed set on Project Management, Monitoring and Control shows your real accuracy, how long you take and where you lose marks.
More Project Management, Monitoring and Control questions
- The critical path of a project at Kaveri Constructions consists of three activities with expected times of 10, 14 and 16 days, and variances…
- A construction firm in Pune has completed building a warehouse and is now handing it over to the client, obtaining acceptance, releasing sta…
- Which feature best distinguishes a project from routine operations in an organisation?
- An activity has optimistic time 6 days, most likely time 9 days and pessimistic time 18 days. What is the variance of its duration under PER…
- A project has a total budget at completion (BAC) of ₹20,00,000. Earned value to date is ₹8,00,000 and actual cost is ₹10,00,000. Assuming th…
- In the project life cycle, which phase is mainly concerned with defining objectives, scope, deliverables and obtaining approval to proceed?