CMA Intermediate · Operations Management and Strategic Management · Project Management, Monitoring and Control
A project has an expected duration of 40 days with a standard deviation of 4 days on its critical path. Given the normal distribution, the area under the curve between the mean and Z = 1.5 is 0.4332. What is the probability of completing the project within 46 days?
The probability is 93.32%. Z = (46 − 40)/4 = 1.5, and adding the 0.5 area below the mean to 0.4332 gives 0.9332. The figure 6.68% is the probability of taking longer than 46 days.
- A43.32%
- B56.68%
- C93.32%Correct
- D6.68%
Explanation
Z = (46 - 40)/4 = 1.5. Probability = 0.5 + 0.4332 = 0.9332, i.e. 93.32%. Choosing 43.32% forgets the 0.5 area below the mean; 6.68% is the chance of exceeding 46 days.
Did you get it right without looking?
One question tells you little. A timed set on Project Management, Monitoring and Control shows your real accuracy, how long you take and where you lose marks.
More Project Management, Monitoring and Control questions
- A project has a total budget at completion (BAC) of ₹20,00,000. Earned value to date is ₹8,00,000 and actual cost is ₹10,00,000. Assuming th…
- In the project life cycle, which phase is mainly concerned with defining objectives, scope, deliverables and obtaining approval to proceed?
- Which feature best distinguishes a project from routine operations in an organisation?
- In a PERT network, an activity has optimistic time 4 days, most likely time 7 days and pessimistic time 16 days. Using the beta-distribution…
- In the traditional project management 'triple constraint', a client of an Indian infrastructure firm demands that the scope be expanded mid-…
- Which tool breaks the total project scope into smaller, hierarchical, manageable deliverables and work packages?