A construction firm in Pune has completed building a warehouse and is now handing it over to the client, obtaining acceptance, releasing staff and recording lessons learned. Which life cycle phase is this?
This is the closure phase. Handing over the deliverable, getting client acceptance, releasing resources and recording lessons learned are the final activities that formally end a project, unlike planning or execution, which occur earlier.
- APlanning
- BExecution
- CClosureCorrect
- DInitiation
Explanation
Handover, client acceptance, release of resources and documentation of lessons learned are the activities of the closure (termination) phase. Execution is the actual construction, and planning precedes it, so those options do not fit.
Did you get it right without looking?
One question tells you little. A timed set on Project Management, Monitoring and Control shows your real accuracy, how long you take and where you lose marks.
More Project Management, Monitoring and Control questions
- During project monitoring, a negative cost variance (CV = EV − AC) indicates which situation?
- An activity has a normal time of 10 days at a normal cost of ₹40,000 and a crash time of 6 days at a crash cost of ₹52,000. Assuming linear …
- A project has an expected duration of 40 days with a standard deviation of 4 days on its critical path. Given the normal distribution, the a…
- In project crashing under the time-cost trade-off method, which activities should be considered first for shortening the project duration?
- In a project network, a delay in an activity that has a total float of 6 days is 4 days. Assuming no other change, what is the effect on the…
- In PERT analysis, why is the probability of completion by a given date calculated using only the critical path's mean and variance?