A project has a total budget at completion (BAC) of ₹20,00,000. Earned value to date is ₹8,00,000 and actual cost is ₹10,00,000. Assuming the current cost performance continues for the remaining work, what is the estimate at completion (EAC = BAC/CPI)?

The estimate at completion is ₹25,00,000. Cost performance index is 8,00,000/10,00,000 = 0.8, so EAC equals budget 20,00,000 divided by 0.8. This assumes the current cost efficiency persists for all remaining work.

  1. A₹22,00,000
  2. B₹25,00,000Correct
  3. C₹30,00,000
  4. D₹12,00,000

Explanation

CPI = EV/AC = 8,00,000/10,00,000 = 0.8. EAC = BAC/CPI = 20,00,000/0.8 = ₹25,00,000. Check: remaining work 12,00,000 at 0.8 efficiency costs 15,00,000; plus 10,00,000 spent gives 25,00,000. The ₹22,00,000 option adds only the overrun of 2,00,000 to BAC.

Did you get it right without looking?

One question tells you little. A timed set on Project Management, Monitoring and Control shows your real accuracy, how long you take and where you lose marks.

More Project Management, Monitoring and Control questions