An operating statement shows a favourable material price variance, an adverse material usage variance and an adverse labour efficiency variance. Which of the following is the most likely single explanation for all three?
The most likely explanation is that cheaper, lower-quality materials were bought. These save money on price but cause more waste and slower, more difficult working, so material usage and labour efficiency both go adverse while the price variance is favourable.
- APurchase of cheaper, lower-quality materialsCorrect
- BPurchase of higher-grade materials than standard
- CAn unexpected rise in hourly wage rates
- DSales volume higher than budget
Explanation
Cheaper material explains the favourable price variance. Lower quality leads to more waste, which gives the adverse usage variance, and more difficult handling or rework, which takes longer and gives the adverse efficiency variance. Higher-grade materials would produce the opposite price pattern. A wage rise affects the labour rate variance, and sales volume does not drive these variances.
Did you get it right without looking?
One question tells you little. A timed set on Variance calculations and analysis shows your real accuracy, how long you take and where you lose marks.
More Variance calculations and analysis questions
- Brindle Co has a standard labour rate of $9 per hour. In June, 3,200 hours were paid at an actual cost of $30,080, of which 150 hours were r…
- Kestrel Ltd budgeted fixed production overheads of $60,000 for the period, based on 12,000 units at 2 labour hours per unit. Actual fixed ov…
- Marlow Co uses absorption costing. Budgeted fixed overheads were $90,000 for 15,000 units, giving an absorption rate of $6 per unit. Actual …
- Brandt plc budgeted to make 1,000 units, with a standard of 2 labour hours per unit and a variable overhead rate of $5 per hour. It actually…
- Ketter Ltd has a standard variable overhead rate of $6 per labour hour. Actual output required 2,000 standard hours, but 2,100 hours were wo…
- Dalton Co makes product P, with a standard of 3 labour hours per unit at $10 per hour. In March it produced 1,200 units using 3,750 hours. W…