Ketter Ltd has a standard variable overhead rate of $6 per labour hour. Actual output required 2,000 standard hours, but 2,100 hours were worked. The variable overhead expenditure variance was $630 favourable. What was the actual variable overhead cost incurred?

Actual variable overhead cost was $11,970. The 2,100 hours worked at the standard $6 rate would cost $12,600, and the $630 favourable expenditure variance means the business spent $630 less than that. The standard hours for output are irrelevant to this calculation.

  1. A$11,970Correct
  2. B$13,230
  3. C$11,370
  4. D$12,570

Explanation

Actual hours at standard rate = 2,100 × $6 = $12,600. A favourable expenditure variance means actual cost was lower: $12,600 − $630 = $11,970. Using standard hours ($12,000) gives $11,370, while adding the variance gives $13,230.

Did you get it right without looking?

One question tells you little. A timed set on Variance calculations and analysis shows your real accuracy, how long you take and where you lose marks.

More Variance calculations and analysis questions