Anand Interiors completed a job with a cost of Rs 1,20,000. During production, abnormal spoilage specific to a customer's special instructions caused by a design change requested by the customer led to extra cost of Rs 9,000 included in that figure. How is this ordinarily treated in job costing?
The Rs 9,000 should be charged to the specific job, because the extra cost arose from that customer's special requirement. Costs of spoilage or rework specific to a job are borne by that job, whereas normal general spoilage goes to overheads.
- ACharged to the specific job since it arose due to the customer's requirementCorrect
- BCharged to costing profit and loss account as abnormal loss
- CSpread over all jobs of the factory through overhead rate
- DIgnored and written off to the next job
Explanation
If rework or spoilage arises because of the special requirements of a particular job, its cost is charged to that job. Only spoilage common to all jobs and normal is absorbed through overheads. Abnormal loss due to avoidable factory inefficiency goes to costing profit and loss, which is not the situation here.
Did you get it right without looking?
One question tells you little. A timed set on Job Costing shows your real accuracy, how long you take and where you lose marks.
More Job Costing questions
- Which of the following best describes the treatment of a job cost sheet in job costing?
- Which of the following best describes a job cost sheet in a job costing system?
- Mehta Printers quoted for Job P-7 at cost plus 25% on selling price (i.e., profit is 25% of the selling price). The job's total cost was ₹96…
- In job costing, which document is used to accumulate the material, labour and overhead costs of a particular job, and from which the total c…
- In job costing, which document is used to collect and record the cost of direct materials, direct labour and overheads for each individual j…
- Kaveri Fabricators is working on Job No. 214. Direct materials cost Rs 48,000 and direct wages are 600 hours at Rs 80 per hour. Factory over…