CA Intermediate · Cost and Management Accounting · Job Costing
In job costing, which document is used to collect and record the cost of direct materials, direct labour and overheads for each individual job as work progresses?
The job cost sheet is the document that accumulates direct materials, direct labour and overheads for a specific job. Other documents such as requisition notes, bills of materials and goods received notes record only parts of the process.
- AJob cost sheetCorrect
- BBill of materials
- CMaterial requisition note
- DGoods received note
Explanation
The job cost sheet accumulates all costs of one job. A material requisition note records only issue of materials, a bill of materials lists the required items, and a goods received note records receipt of goods.
Did you get it right without looking?
One question tells you little. A timed set on Job Costing shows your real accuracy, how long you take and where you lose marks.
More Job Costing questions
- Mehta Engineering prices jobs at cost plus 25% on selling price (that is, profit is 25% of the selling price). Job K-7 has direct materials …
- Sharma Fabricators absorbs factory overhead at Rs 40 per machine hour. Job J-21 used direct material of Rs 18,000, direct labour of Rs 12,00…
- A job was completed by Sunrise Tools after the company gave a customer a quotation. During the job, a quantity of materials worth Rs 4,000 i…
- Gupta Printers quotes jobs at cost plus 25% on selling price. Job P-7 has direct material Rs 24,000, direct labour Rs 16,000 and overheads a…
- Iyer Engineering absorbs factory overhead on direct labour hours. Budgeted overhead for the year was Rs 6,00,000 for 40,000 hours. Actual ov…
- Rao Engineering absorbs factory overheads on machine hours. Budgeted overheads for the year were ₹7,20,000 for 24,000 machine hours. Actual …