CA Intermediate · Advanced Accounting · AS 7 Construction Contracts

Aravalli Projects Ltd has a fixed price contract of ₹1,00,00,000. Year 1: costs incurred ₹20,00,000, further estimated cost ₹60,00,000. Year 2: costs incurred to date ₹56,00,000, further estimated cost ₹24,00,000. Stage of completion is based on cost proportion. Advance received is ignored. What is the contract revenue recognised in Year 2 and the profit recognised in Year 2?

Year 2 revenue is ₹45,00,000 and profit is ₹9,00,000. Cumulative stage of completion is 70 percent (56 of 80 lakh), giving cumulative revenue of ₹70,00,000, less ₹25,00,000 recognised in Year 1. Year 2 costs are ₹36,00,000, so profit is 45 lakh minus 36 lakh.

  1. ARevenue ₹45,00,000; profit ₹9,00,000Correct
  2. BRevenue ₹70,00,000; profit ₹14,00,000
  3. CRevenue ₹45,00,000; profit ₹5,00,000
  4. DRevenue ₹50,00,000; profit ₹10,00,000

Explanation

Total cost estimate Year 1 = 80 lakh; stage 25%; revenue 25 lakh; cost 20 lakh; profit 5 lakh. Year 2 total estimate = 56+24 = 80 lakh; stage 70%; cumulative revenue 70 lakh; Year 2 revenue = 70−25 = 45 lakh. Year 2 cost = 56−20 = 36 lakh; profit = 45−36 = ₹9,00,000. The ₹70,00,000 option is cumulative revenue, not the year's revenue.