CA Intermediate · Advanced Accounting · AS 7 Construction Contracts
Bharat Infra Ltd is building a bridge for a state road authority under a construction contract. The contract does not provide for reimbursement of head-office costs. While working out the contract costs to be recognised under AS 7, the accountant lists four items. Which item must NOT be included in contract costs?
Head-office general administration costs are excluded from contract costs when the contract does not reimburse them. Site supervisor wages, depreciation of plant used on the site and site insurance are directly related or allocable to the contract, so AS 7 includes them in contract costs.
- AWages of site supervisors working on the bridge
- BDepreciation of cranes used only at the bridge site
- CGeneral administration costs of the head office, with no reimbursement under the contractCorrect
- DInsurance premium paid for the bridge site
Explanation
AS 7 includes costs directly related to the contract and costs attributable to contract activity in general that can be allocated to it, such as insurance and plant depreciation. General administration costs are excluded unless the contract specifically reimburses them. Site supervision, site-specific depreciation and insurance are all valid contract costs.
Did you get it right without looking?
One question tells you little. A timed set on AS 7 Construction Contracts shows your real accuracy, how long you take and where you lose marks.
More AS 7 Construction Contracts questions
- Yamuna Engineers Ltd. has a fixed price contract of Rs 100 lakh. At year-end, costs incurred are Rs 40 lakh, which include Rs 6 lakh of mate…
- Ganga Projects Ltd. has a fixed price contract of Rs 300 lakh. At the end of Year 1, costs incurred were Rs 150 lakh and estimated total cos…
- Konkan Infra Ltd. entered into a fixed price contract with a State road corporation for Rs 80 lakh. Up to the reporting date, contract costs…
- Konark Builders enters into a fixed price contract to construct a bridge for a contract price of ₹50,00,000. At the end of Year 1, costs inc…
- Navjyot Constructions is building a bridge for a state government. Its accountant is listing items for the contract cost under AS 7. Which o…
- Rao Projects has a Rs 200 lakh fixed price contract. Cost incurred to date is Rs 120 lakh including Rs 20 lakh of steel purchased and delive…